Weeks of November 3 and November 10, 2025
Global
Working Hours
-
Trackwork construction activities for the remainder of the project
are ongoing and will take place from 6AM to 7PM.
Site Testing
-
Testing in Go Hammond and Town of Munster, Indiana on December 1st
and 2nd during daytime hours.
View Facebook Post.
-
Various testing activities throughout the eight-mile project area.
Hammond
Station Construction
-
Contractor finishing elevator inspection at Hammond Gateway
Station.
Gate Crossing Loop Detector Installation and Testing
-
Working at Sheffield/SSL and Hohman/SSL week of 11/3/2025. Roadway
flaggers will be controlling traffic through the grade crossing.
-
Working from Douglas to 173rd starting on 11/13/2025.
-
165th Street
- Work begins on 11/17 around 9PM through 11/18 5AM.
- Work will be done under flagger protection.
Munster
Station Construction
-
Munster-Dyer West Access
-
Landscaping Activities
-
Trucking operations on Allison Road/Columbia Ave/Sheffield
Ave. Minimal impacts to vehicular traffic.
-
Parking Lot Construction
-
Landscaping Activities
-
Trucking operations on Allison Road, minimal impacts
to vehicular traffic.
Gate Crossing Loop Detector Installation and Testing
-
Working at Fisher Street and Ridge Road
-
Ridge Road work begins on 11/19 around 9PM through 11/20 5AM.
Work will be done under flagger protection.
Dyer
Flatwork and Asphalt Paving
-
Finishing emergency access roads
-
Removal of material, pouring of new curb and sidewalk, asphalt
installation and bollard installation.
-
Trucking operations on Main Street, minimal impacts to
vehicular traffic.
For additional information about work in your area, please contact
219.296.6004.